Interchange Improvements Ease Your Commute

 
 
TABLE OF CONTENTS
-I-4/SR 408 Interchange Improvements Reduce Congestion for Drivers
-Final Bridge Over I-4 Completed on Volusia County Project
-Drive Toward a Greener Florida with FDOT's Free 511 Service
 
 
Project Updates
I-4 Construction Schedule

Interim SR 408 Interchange Improvements
• Start: April 2006
• Anticipated completion: December 2008

SR 472 to SR 44 Widening
• Start: March 2007
• Anticipated completion: summer 2008

I-4/SR 408 Interchange Improvements Reduce Congestion for Drivers

New ramp from westbound SR 408 to eastbound I-4 

FDOT continues to reach milestones as the project in downtown Orlando passes the two-year mark.
Full Story...

 
Final Bridge Over I-4 Completed on Volusia County Project

New interchange at SR 44 

Interchange improvements at SR 44 allow drivers to reach the Volusia County Fairgrounds and neighboring counties with ease.

Full Story...

 
Drive Toward a Greener Florida with FDOT's Free 511 Service
Each Central Florida driver wastes an average of 23 gallons of fuel a year while idling in traffic jams, according to the Texas Transportation Institute (TTI). The free 511 traffic information service can help you save gas by avoiding convestion.
Full Story...

SUBSCRIBE
Interested in receiving this information? Subscribe here!
TELL-A-FRIEND
Know someone who would be interested in receiving this information? Click here to tell them about it.
Contact Information
Jim Martin
I-4 Public Information Office
888-454-4884

Media Contact:
Derek Hudson 
I-4 Public Information Office
407-571-6766
407-666-7605 (After Hours)

 
  Click here to unsubscribe. | Developed & Powered By Global-5